Mesquite Street Reconstruction
Company
Western Rock Products
Project Type
Asphalt
Location
Mesquite
Southern Utah
Owner:ÌýMesquite CityÌý
General Contractor:ÌýWestern Rock ProductsÌý
Start Date:ÌýDecember 30, 2019Ìý
Completion Date:ÌýFebruary 11, 2020Ìý
Subcontractors or Key Contractors:ÌýCoughlin Company (Roto milling); Straight Stripe Painting (Striping); Mesquite General Contracting (Grading; Manholes and water valves).Ìý
Materials Used and Quantities:Ìý
- 14,763.91 tons of HMA
The City of Mesquite was very pleased with the project. Western Rock Products were very responsive to any questions and concerns that the City of Mesquite had. A portion of the project included the rehabilitation of a local roadway in front of the local middle school. The City of Mesquite requested that the work be done during the holiday break as to not adversely affect the middle school traffic. Western Rock Products Companies were very willing to accommodate this request and it made for a much smoother project. This project was a huge success and we look forward to working with Western Rock Products Companies again in the future.